Objective and Background
Production of syngas from municipal solid waste (MSW) in Istanbul through thermal gasification
and its conversion to electricity using a high-efficiency gas engine/turbine combination:
technical and economic feasibility + 1–3 t/h pilot design.
Maya’s doctoral expertise (gasification, syngas optimization) defines the core methodology.

Targets (quantitative):
- Annual waste processed: 100,000 tons (first phase)
- Net electricity capacity: 25 MW; annual generation: ≈180 GWh
- CO₂e reduction: ≈95 kt/year (vs. incineration-based scenario)
- LCOE target: ≤ ₺2.1/kWh
Scope and Assumptions
- Feedstock: Lower heating value 8–11 MJ/kg; moisture 15–35%; composition: organics 45%, paper/cardboard 18%, plastics 12%, textiles 6%, inert 19%.
- Gasifier: Circulating Fluidized Bed (CFB), air + enriched oxygen hybrid, bed material sand/olivine.
- Gas cleaning: Cyclone + scrubber + tar removal (catalytic cracker) + cooling/filtration.
- Power: 2 × 12.5 MW gas engines (high cycle efficiency, with CHP option).
- Grid: 154 kV connection; option for integration with heat recovery.
Methodology (Step by Step)
- Data Collection – Seasonal sampling at 3 Istanbul transfer stations, proximate/ultimate analysis; moisture, ash, volatiles, elemental C/H/O/N/S.
- Scaling & Mass-Energy Balance – Aspen Plus with RGibbs approach; syngas composition (H₂, CO, CH₄, CO₂, tar) depending on waste moisture.
- Moisture Optimization – Drying + process heat to determine optimum range of 15–25%.
- Figure-1: Moisture Content vs Net Power Output trend:

- Figure-1: Moisture Content vs Net Power Output trend:
- Gas Cleaning Sizing – Targets: tar < 50 mg/Nm³, dust < 5 mg/Nm³; pressure drop, water/chemical consumption.
- Emission Comparison – Incineration (baseline) vs gasification (with filtration).
- Figure-2: Emission Comparison Chart (Base=100)

- Figure-2: Emission Comparison Chart (Base=100)
- Net-back Electricity Cost (LCOE) – CAPEX (reactor, cleaning, power), OPEX (operations, maintenance, staff), ash/slag disposal; revenues (electricity, heat, waste intake, optional carbon credits).
- Legal Compliance – Turkish regulations on waste incineration/gasification emission limits, RDF criteria, environmental permits/EIA process roadmap.
- Pilot Design – 1–3 t/h modular CFB pilot: fuel preparation, reactor, gas cleaning skid, 500 kW engine, data collection (GC, FTIR) and safety (HAZOP).
Sample Sizing Outputs
- Reactor load: 3.2 t/h (dry basis) @ 850–900 °C
- Syngas HHV: 4.8–6.2 MJ/Nm³ → engine efficiency ~38%
- Specific electricity yield: 450–520 kWh/ton waste (at 20% moisture)
- Water for tar scrubbing: 1.2–1.6 m³/ton syngas; water treatment integration required
Deliverables
- Feasibility report (120+ pages), Aspen files, PFD/PI&D, pilot basic design, preliminary Environmental Impact study, economic model (xls), risk/HAZOP matrix.
Timeline (12 Months)
1–3: Waste analysis and Aspen modeling
4–6: Gas cleaning and engine integration simulations
7–9: Pilot design + procurement specifications
10–12: Site installation plan + final feasibility
Risks and Mitigations
- Tar/Fouling: Catalytic cracker + periodic steam injection
- Moisture fluctuation: Pre-drying and flow-balancing bunker
- Permitting: Early authority consultation + monitoring plan
Finance (summary, excl. VAT)
- CAPEX: ~₺950 million
- OPEX: ₺180 million/year
- Revenue: Electricity sales (outside FIT), heat sales (CHP), waste intake fees
- Payback: 6.5–8 years (depending on scenario)
Conclusion: Gasification, at the scale of Istanbul, has the potential to reduce CO₂e by ~32% and NOx by ~45% compared to incineration-based reference; strong indicators in energy recovery and sustainability.